Activity
Mon
Wed
Fri
Sun
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
What is this?
Less
More

Owned by Vlad

This community shares real lifting case studies, consultancy insights, and site-proven lessons covering cranes, supervision, planning, and execution.

161 contributions to Safe Lifting
Unsecured 231kg Load Crushes Worker During Forklift Operation
During a routine loading operation, a forklift was being used to lift heavy electrical equipment onto a flatbed lorry. The equipment weighed approximately 231kg. The load was not secured to the forklift. A worker was acting as a spotter, standing close to the moving equipment. The load fell from the forklift and crushed the worker. The worker suffered severe brain and spinal injuries and now requires 24-hour care. A routine operation resulted in life-changing injuries. What Went Wrong ● Unsecured Load – The equipment was not positively restrained. ● No Lift Plan – The operation had not been properly planned or risk assessed. ● Unsafe Positioning – Workers were expected to physically steady heavy equipment. ● Poor Equipment Selection – A lorry-mounted crane was available but not used. ● Unsafe Routine – Repeatedly carrying out the task had created acceptance of an unsafe method. Key Lessons Learned ● A routine lift can still be dangerous. ● Never rely on workers to physically stabilise an unsecured heavy load. ● Select suitable lifting equipment before starting the operation. ● Keep personnel outside the line of fire. Safety Recommendations ● Prepare a suitable lifting plan and risk assessment. ● Secure loads using suitable, approved arrangements. ● Use available lifting points and appropriate equipment. ● Establish exclusion zones around loading activities. ● Never allow workers to stand where an unstable load could fall. ● Stop operations when the load cannot be safely controlled. Incident Source HSE prosecution report – 16 October 2026. The company was fined £4 million following a prosecution under Section 2(1) of the Health and Safety at Work etc. Act 1974. Regulatory Mapping ● LOLER Reg. 8 – Lifting operations must be properly planned, supervised and carried out safely. ● PUWER Reg. 4 – Work equipment must be suitable for the intended operation. ● PUWER Reg. 20 – Work equipment must be stabilised where necessary for health and safety. ● BS 7121 principles – Relevant good-practice lessons on planning, load control and keeping personnel clear, where applicable.
0
0
Unsecured 231kg Load Crushes Worker During Forklift Operation
Cantilevered Loading Platforms: Is the Platform Ready for the Lift?
Cantilevered loading platforms are commonly used on high-rise construction projects to receive materials from tower cranes. On 20 October 2026, the CPA published new industry guidance covering the safe selection, installation, operation, inspection and removal of these platforms. The lifting operation must consider more than the crane’s lifting capacity. What Can Go Wrong ● The platform’s permitted loading is not confirmed. ● Materials are placed incorrectly or concentrated in one area. ● The platform is used without confirmation that installation and inspections are complete. ● Crane operators and landing teams have unclear communication. ● Personnel enter dangerous positions during load landing. ● The AP and Temporary Works Coordinator fail to coordinate responsibilities. Key Lessons Learned ● The crane’s capacity does not determine the platform’s safe loading limit. ● The AP must consider the complete lifting arrangement, including the landing location. ● Temporary works approval and platform readiness must be confirmed before use. ● Material weight, positioning and loading sequence must be controlled. Safety Recommendations ● Confirm platform capacity and manufacturer requirements. ● Coordinate the lift plan with temporary works documentation. ● Verify installation, inspection and authorisation before loading. ● Establish safe access and exclusion zones. ● Agree communication between the crane operator and landing team. ● Plan platform installation and removal as controlled operations. Incident Source CPA Crane Interest Group and Tower Crane Interest Group – 20 October 2026. New industry guidance written by Conquip. This is a guidance-based safety study, not an accident investigation. Regulatory Mapping ● LOLER Reg. 8 – Safe planning and execution of crane lifting operations. ● PUWER Regs. 4 and 6 – Suitability and inspection of work equipment, where applicable. ● CDM 2015 Regs. 13 and 15 – Coordination and management of construction activities. ● BS 7121 principles – Safe lifting arrangements, landing areas and supervision.
0
0
Cantilevered Loading Platforms: Is the Platform Ready for the Lift?
Damaged Chains: Three-Tonne Steel Beam Falls into Molten Zinc
During a steel galvanising operation, a beam weighing nearly three tonnes was being lifted above a bath of molten zinc. The lifting chains were damaged and deteriorated. The chains had not received their required thorough examination. An incorrect slinging configuration exceeded the chains’ safe lifting capacity. The chain failed, dropping the beam into the molten zinc. The impact created a wave of molten metal that struck a worker, causing burns to 40% of their body. The worker required 13 operations and suffered life-changing injuries. What Went Wrong ● Damaged Accessories – Deteriorated chains remained in service. ● Missing Examination – Mandatory thorough examination requirements were not met. ● Incorrect Slinging – The configuration exceeded the permitted chain capacity. ● Inadequate Risk Assessment – Chain checks and correct slinging arrangements were not addressed. Key Lessons Learned ● A valid certificate does not replace pre-use inspection. ● Chain slings exposed to aggressive environments require additional attention. ● The WLL must be suitable for the actual slinging configuration. ● Damaged lifting accessories must be immediately removed from service and quarantined. Safety Recommendations ● Inspect lifting chains before use. ● Check examination records and any applicable examination scheme. ● Verify sling configuration, angles and working load limits. ● Quarantine damaged, corroded or deteriorated accessories. ● Include environmental exposure and accessory selection in the lift plan. Incident Source HSE prosecution report – 20 October 2026. The company was fined more than £500,000. The reported conviction was under the Health and Safety at Work etc. Act, rather than LOLER. Regulatory Mapping ● LOLER Reg. 8 – Lifting operations must be properly planned and safely carried out. ● LOLER Reg. 9 – Lifting accessories require appropriate thorough examination. ● PUWER Reg. 5 – Work equipment must be maintained in an efficient state and good repair. ● BS 7121 principles – Correct accessory selection, inspection and safe slinging arrangements.
0
0
Damaged Chains: Three-Tonne Steel Beam Falls into Molten Zinc
Distracted Slinger/Signaller: Using a Mobile Phone During Lifting Operations
During pipe installation works, a 360° excavator was being used to lift and position materials into an excavation. A Slinger/Signaller was responsible for directing the machine operator and controlling the lifting operation. ● The Slinger/Signaller was observed using a mobile phone while involved in the lifting activity. ● Several workers were positioned close to the excavation and lifting area. ● The operation required continuous attention, clear communication and awareness of personnel movements. ● Using a mobile phone created a distraction at a critical stage of the operation. A moment of distraction during lifting operations can lead to serious injuries or fatalities. What Went Wrong ● Distraction During Lifting – The Slinger/Signaller’s attention was divided between the mobile phone and the lifting activity. ● Reduced Situational Awareness – Phone use could prevent the signaller from identifying unexpected machine or load movements. ● Communication Risk – The operator may not receive timely instructions or warnings. ● Personnel Exposure – Workers positioned close to the lifting area could be exposed to swinging loads, crushing or entrapment. ● Unsafe Behaviour – Personal phone use is incompatible with actively controlling a lifting operation. Key Lessons Learned ● A Slinger/Signaller must remain focused on the lifting operation. ● Never use a personal mobile phone while actively directing lifting movements. ● Maintain continuous awareness of the load, machine and surrounding personnel. ● If attention is required elsewhere, stop the lifting operation first. ● A distracted signaller can compromise the safety of the entire lifting team. Safety Recommendations ● Prohibit personal mobile phone use while actively signalling or controlling lifting operations. ● Ensure clear communication between the machine operator and Slinger/Signaller. ● Stop lifting immediately if the signaller becomes distracted or cannot maintain control. ● Establish suitable exclusion zones around excavators and suspended loads.
0
0
Distracted Slinger/Signaller: Using a Mobile Phone During Lifting Operations
Stop Instruction Overridden: Lift Supervisor Blamed After Dangerous Lift
During lifting operations involving an LR 1160 crawler crane, long formwork shutters were scheduled to be lifted in sustained winds of approximately 11 m/s or 25 mph. ● The crane operator raised concerns about the wind conditions and stated that he was not comfortable proceeding. ● The Lift Supervisor agreed with the operator and instructed the Lifting Coordinator to stop the operation. ● The coordinator dismissed the supervisor’s concerns and approached the operator directly, encouraging him to proceed because the Project Manager wanted the lift completed. ● During the first lift, the shutter began swinging and rotating violently, creating a serious risk of striking the crane cabin. ● The operator lowered the load to the ground in an attempt to prevent a collision. ● Afterwards, the coordinator blamed the Lift Supervisor for failing to control the operation, despite having overridden his stop instruction. What Went Wrong ● Stop Instruction Ignored – The Lift Supervisor’s decision was overridden without resolving the safety concerns. ● Management Pressure – Completing the lift was prioritised over the objections raised by the lifting team. ● Operator’s Concerns Dismissed – The operator had already identified that the conditions were unsuitable. ● Loss of Load Control – The large shutter became unstable in the wind. ● Breakdown in Supervision – The coordinator intervened directly instead of escalating the concern to the Appointed Person. ● Blame Culture – Responsibility was shifted onto the Lift Supervisor after the operation went wrong. Key Lessons Learned ● A Lift Supervisor must have the authority to stop an unsafe lifting operation. ● A coordinator or manager must not override a safety stop without a competent reassessment and safe authorisation to restart. ● Crane operating wind limits do not automatically establish safe limits for large, wind-sensitive shutters. ● The crane operator has the right to refuse a lift they consider unsafe. ● A supervisor cannot be expected to control a lifting operation when their stop instruction has been disregarded.
0
0
Stop Instruction Overridden: Lift Supervisor Blamed After Dangerous Lift
1-10 of 161
Vlad Lupu
4
78 points to level up
@vlad-lupu-5718
Founder of Wolf Lifting Dynamics | CPCS Appointed Person (A61) Helping teams deliver safer lifts. "Learn from incidents before they become accidents"

Active 2d ago
Joined Dec 25, 2025
Corby