Man... what a show it can be sometimes with the city. All for good reason so we have to figure a way to work through it. What's next?
- Some grading will be needed (see piles of dirt hanging around some places): Monday
- Sod delivery: (scheduled for Monday afternoon)
- Sod installation: (scheduled for Tuesday morning) I only go about 10' AWAY from the house... otherwise, sod can get REAL expensive quickly. We're at around $175/pallet. A pallet covers around 400-450 sqft.
- Exterior paint: You have to power wash the house first (scheduled for Wed morning - which helps water the grass) plus some additional caulking. Actual paint will go on Thursday
- Interior clean-up: Any time this coming week... it's time to get it finalized.
Who has additional updates on their projects?
B2R,
Juan-