QUESTION 3 PMP
After the transition and completion of a large equipment installation project, the project manager receives a request from the customer to add some operational cost to the project budget for team-building activities. The project was completed under budget, project contingency reserves were not spent, and the team-building activities will ensure the operational team's optimal performance.
What should the project manager do?
  1. A.Reject the request and close the project financials.
  2. B.Perform the integrated change control process.
  3. C.Approve the expenditure to ensure customer satisfaction.
  4. D.Document the request in the lessons learned repository.