PMP Audit- Failed
I've been selected for auditing and have uploaded the corresponding documentation. I've been told that the project descriptions are incorrect: this is the message. My analisis is that is or i described badly the program or is not permited group projects. I will put my descriptions in the first comment i would apreciate your thoughts, specially if some task sound like operations and not projects of if the projects are similar. the two projects i work as a project manager... thanks you in advance
.-----------------------------
Eligibility Not Met: Projects are not presented individually
PMI requires that projects be documented individually, regardless of the number of projects a candidate is documenting.
The experience entry on your application appears to include grouped and combined project experience. We require that projects be documented as individual entries on your application, regardless of the number of projects a candidate is documenting.
Additional Comments:
Projects that are documented on the application should meet the following criteria:
-Tasks documented are project tasks, and not routine, operational or administrative in nature
-Projects are documented individually and must be for a professional association/organisation; multiple projects are not documented as one
-Project titles reflect the true project title, and not the candidate’s role or function
-Deliverables are documented clearly
Project descriptions should consist of the following:
-A brief, one-sentence project objective
-Your role and responsibility on the project team
-A brief, one-sentence project outcome.
0
4 comments
Angel Guerra
1
PMP Audit- Failed
PMP
skool.com/pmp
Join our PMP hub to post questions, form study groups, and access free classes. Elevate your project management skills!
Leaderboard (30-day)
Powered by