QUESTION 4 PMP
During sprint planning, an agile team and product owner identified that the team should be able to finish five user stories. However, during the sprint, the team worked on more than five stories but did not complete any stories at all.
What should the project manager do?
  1. A.Clarify priorities with the team.
  2. B.Create smaller stories in the future.
  3. C.Review the definition of done (DoD).
  4. D.Update the product release plan.