Critical Path Theory
Hi Andrew, I was looking at the Critical Path Theory example you have in the note. To be specific the one that has the critical path as A, D, F, G, H, Finish = 23. My question is why is A, B, E, F, G, H = 24 not one of the paths and ultimately the critical path? Thanks.