The project manager, Mary, has completed the scope statement and the WBS for a small project. She has approached the sponsor about gaining approval for the scope baseline. Upon inspection, the sponsor decided the scope baseline doesn’t have enough information in it. What is the best action Mary can take?
A) Work with the team and create a WBS dictionary
B) Go back to the collect requirements processes to ensure all requirements were added to the scope baseline
C)Ask the sponsor to write the scope
D) Work with the team to create a project schedule and cost baseline
In the above question, why is A correct and not B?