This is one of the practice questions from Andrew by I'm struggling to understand the correct answer which is "b". I thought it should be "a"? Can someone please help me to understand it? Thanks!
Company XYZ has been executing a new business development project for the last 4 months. A few stakeholders have requested changes to the scope and have gotten them approved. When a change is approved, what is the next best step to conduct on a project?
Select one:
a. Execute the approved change request in the process of direct and manage project work
b. Execute the approved change request in the process of monitor and control project work
c. Validate the change in the validate scope process
d. Close the change request in the close project or phase process