Activity
Mon
Wed
Fri
Sun
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
What is this?
Less
More

Memberships

PMP

10.8k members • Free

4 contributions to PMP
PMP mock exams
Hey Andrew, I completed the mock exam in the 35 hour course and got 77%. Since then I’ve purchased your 2024-pmp exam practice-mock test simu and completed 2 x mock exam so far but am getting 62%. Are these exams meant to be harder? Or it’s at the level of the actual exam.
Clarification on an exam question
Hi Andrew I did a practice exam from your 2024 Udemy exam prep and I came across these two questions that I got wrong but don’t understand the explanation. Are you able to assist? A complex project involving multiple stakeholders is currently in progress. As per the project management office (PMO) requirements, all project status reports and other project-related documents are stored in a centralized repository. During a review of the repository, the project manager noticed that some documents were either missing or not up-to-date. What should the project manager do to address this situation? Correct answer: Engage in discussions with the project sponsor to streamline the documentation requirements. My answer: Collaborate with the team leaders to ensure the necessary project reports are updated
Clarification on an exam question
Hi Andrew I did a practice exam from your 2024 Udemy exam prep and I came across these two questions that I got wrong but don’t understand the explanation. Are you able to assist? Q 1 - no where in the question does it say the risk was identified during the planning phase 1. A project manager is overseeing the production of a specific machine in a factory, which was contracted through a foreign supplier. However, just before the delivery of the final two components, the supplier informs the project manager that they require a renegotiation of prices, threatening non-delivery if the prices are not revised. What should be the project manager's initial action to address this situation? Correct response: Activate the predefined response plan for this risk event. The answer I picked: Collaborate with the supplier to mitigate cost impact through negotiations
1
0
1-4 of 4
Sayeh Woods
1
3points to level up
@sayeh-woods-6412
Practice Manager -PMO

Active 580d ago
Joined May 11, 2024
Powered by