From the test simulator:
Question 92
Incorrect
A project manager is leading a website development project when team members begin adding small enhancements that weren't in the approved requirements. A developer adds extra animation features because "it will look better," and a designer creates additional page layouts beyond what was specified. These additions accumulate over several weeks without formal approval, and the project falls behind schedule.
What problem is the project experiencing?
Your answer is incorrect
Gold plating
Poor quality management
Correct answer
Scope creep
Resource constraints
Edit: after rereading the further explanation, I guess it's about the intentionality and the awareness of the entire team?
From the explanation of why Gold plating is wrong:
Gold plating refers to deliberately adding features or deliverables beyond the agreed project scope, aiming to exceed expectations or enhance quality, even if the client didn't request them. This is typically intentional and done with the project team's awareness.
Scope creep is when uncontrolled and unauthorized changes or additions are made to the project scope, often without formal approval, as seen in this scenario. These changes accumulate over time and lead to schedule delays or other issues.